Nearly $200 Billion Worth of Data Center Projects Have Been Blocked or Delayed This Year
While major tech companies are racing to build massive data centers across the U.S., local communities are increasingly fighting back and in some cases winning. Citing data from Data Center Watch, Bloomberg reports that between April and June, at least 45 data center projects worth nearly $68 billion were blocked or delayed. That’s on top of another 75 projects valued at roughly $130 billion that were disrupted during the first quarter of the year.
- ▪While major tech companies are racing to build massive data centers across the U.S., local communities are increasingly fighting back and in some cases winning.
- ▪Citing data from Data Center Watch, Bloomberg reports that between April and June, at least 45 data center projects worth nearly $68 billion were blocked or delayed.
- ▪That’s on top of another 75 projects valued at roughly $130 billion that were disrupted during the first quarter of the year.
Gizmodo files mainly under tech. We currently carry 1,203 of its stories.
Story provenance
Source · retrieval · rights · ranking — open for full record
inspect →
Story provenance
Attribution is not the same as permission. This drawer separates discovery metadata, excerpts, WeSearch-generated summaries, reuse status, and whether the publisher receives the visit. Nothing here claims a legal grant the publisher has not made.
Record
| Original publisher | Gizmodo |
| Canonical URL | https://gizmodo.com/nearly-200-billion-worth-of-data-center-projects-have-been-blocked-or-delayed-this-year-2000815054 |
| Publication time | Mon, 21 Sep 2026 21:10:29 +0000 |
| Retrieval time | 2026-09-21T21:13:49.143Z |
| Last seen | 2026-09-21T21:13:49.143Z |
| Headline source | Publisher (no WeSearch rewrite) |
| Excerpt source | publisher body |
| Excerpt method | First ~120 words (~800 chars) of extracted publisher body, fair-use limited. |
| Summary | WeSearch · cerebras-chat (WeSearch summarizer) |
| Summary source text | contentText |
| Citation coverage | Summary is a WeSearch-generated derivative; primary citation is the original publisher URL. |
| Cluster | gD8QWkVAWaS- · 1 stories |
| Cluster logic | Grouped by semantic title/content similarity across sources within a rolling window. Same-publisher template collisions are excluded from coverage comparison. |
| Ranking reason | Story pages are not engagement-ranked. Hub feeds use recency, with optional source-diversified chronological ordering (cap consecutive stories per source). No personalized ranking. |
| Publisher visit | Yes — open original |
| Substitutes article? | No — link-out required for full text |
Rights status (four layers)
WeSearch handling by dimension
| Indexing | May the item be indexed (stored, ranked, made findable)? | Allowed |
| Snippet | May a short excerpt of the publisher's text be shown? | Allowed |
| AI summary | May WeSearch generate its own short summary of the article? | Limited |
| Retrieval / RAG | May the content be exposed for third-party retrieval-augmented generation? | Not asserted |
| Model training | May the content be used to train AI models? | Not asserted |
| Commercial reuse | May the content be reused commercially? | Not permitted |
Basis: Derived from the published RSS/Atom feed. Contact: [email protected]. Reviewed: 2026-07-24.
Opening excerpt (first ~120 words) tap to expand
While major tech companies are racing to build massive data centers across the U.S., local communities are increasingly fighting back and in some cases winning. Citing data from Data Center Watch, Bloomberg reports that between April and June, at least 45 data center projects worth nearly $68 billion were blocked or delayed. That’s on top of another 75 projects valued at roughly $130 billion that were disrupted during the first quarter of the year. The figures come from Data Center Watch, a project from 10a Labs, that tracks grassroots opposition to data center development across the country. Collectively, that means nearly $200 billion worth of proposed data center projects ran into delays or were blocked during the first half of 2026.
…
Excerpt limited to ~120 words for fair-use compliance. The full article is at Gizmodo.