Oracle sends force majeure notice on its New Mexico Stargate data center
Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday. Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way. Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources.
- ▪Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday.
- ▪Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way.
- ▪Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources.
4 outlets in our directory ran this story, first to last over 4 hours. All of the coverage we found sits in one bucket: centre. That one-sidedness is itself worth noticing.
- ▪ Oracle invokes force majeure on New Mexico AI data center — Hacker News (AI / LLM)
- ▪ Oracle Invokes Force Majeure in Aim to Protect Itself From Data Center Cost Overruns — The Information
- ▪ Oracle Cites 'Force Majeure' to Shield Itself on Controversial Data Center — Hacker News (Front Page)
TechCrunch files mainly under tech. We currently carry 1,035 of its stories.
Story provenance
Source · retrieval · rights · ranking — open for full record
inspect →
Story provenance
Attribution is not the same as permission. This drawer separates discovery metadata, excerpts, WeSearch-generated summaries, reuse status, and whether the publisher receives the visit. Nothing here claims a legal grant the publisher has not made.
Record
| Original publisher | TechCrunch |
| Canonical URL | https://techcrunch.com/2026/09/24/oracle-sends-force-majeure-notice-on-its-new-mexico-stargate-data-center/ |
| Publication time | Thu, 24 Sep 2026 18:11:44 +0000 |
| Retrieval time | 2026-09-24T18:15:28.387Z |
| Last seen | 2026-09-24T18:15:28.387Z |
| Headline source | Publisher (no WeSearch rewrite) |
| Excerpt source | publisher body |
| Excerpt method | First ~120 words (~800 chars) of extracted publisher body, fair-use limited. |
| Summary | WeSearch · cerebras-chat (WeSearch summarizer) |
| Summary source text | contentText |
| Citation coverage | Summary is a WeSearch-generated derivative; primary citation is the original publisher URL. |
| Cluster | Co0VYm51ASpU · 4 stories |
| Cluster logic | Grouped by semantic title/content similarity across sources within a rolling window. Same-publisher template collisions are excluded from coverage comparison. |
| Ranking reason | Story pages are not engagement-ranked. Hub feeds use recency, with optional source-diversified chronological ordering (cap consecutive stories per source). No personalized ranking. |
| Publisher visit | Yes — open original |
| Substitutes article? | No — link-out required for full text |
Rights status (four layers)
WeSearch handling by dimension
| Indexing | May the item be indexed (stored, ranked, made findable)? | Allowed |
| Snippet | May a short excerpt of the publisher's text be shown? | Allowed |
| AI summary | May WeSearch generate its own short summary of the article? | Limited |
| Retrieval / RAG | May the content be exposed for third-party retrieval-augmented generation? | Not asserted |
| Model training | May the content be used to train AI models? | Not asserted |
| Commercial reuse | May the content be reused commercially? | Not permitted |
Basis: Derived from the published RSS/Atom feed. Contact: [email protected]. Reviewed: 2026-07-24.
Opening excerpt (first ~120 words) tap to expand
Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday. Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way. Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources. Instead, the notice would allow the company to delay payments should the facility miss its 2028 target to come online. The notice also comes as AI data center construction faces growing scrutiny nationally, and as developers take on steep costs to build capacity for customers like OpenAI. Oracle maintains that it does not expect a delay.
…
Excerpt limited to ~120 words for fair-use compliance. The full article is at TechCrunch.