WeSearch

South Central Railway completes 203-km Kazipet-Balharshah rail tripling works

The Hindu Bureau· ·1 min read · 0 reactions · 0 comments · 2 views
#south#central#railway#completes#kazipet-balharshah
South Central Railway completes 203-km Kazipet-Balharshah rail tripling works
TL;DR · WeSearch summary

It also serves several coal and cement sidings along the route, resulting in heavy traffic congestion and near-saturation of line capacity over the years.To decongest the route, SCR initially completed tripling works on the 33-km Raghavapuram-Mandamarri section in 2016. Subsequently, tripling and electrification of the remaining Kazipet-Balharshah stretch were sanctioned during 2015-16. The project covers 203 km, of which 159 km falls in Telangana and 44 km in Maharashtra.

Key facts
Original article
The Hindu — Top · The Hindu Bureau
Read full at The Hindu — Top →
Opening excerpt (first ~120 words) tap to expand

South Central Railway (SCR) has completed the 203-km Kazipet-Balharshah rail tripling project with the commissioning of the final 11-km stretch between Asifabad Road and Sirpur Kaghaznagar, along with electrification works and a major bridge across the Bibra River.Seamless movement on Grand Trunk routeThe ₹3,000-crore project, comprising track tripling and electrification between Kazipet and Balharshah, is expected to enhance operational efficiency and facilitate seamless movement of trains on the busy Grand Trunk route.A busy sectionThe Kazipet-Balharshah section is a crucial rail corridor linking northern and southern India.

Excerpt limited to ~120 words for fair-use compliance. The full article is at The Hindu — Top.

Anonymous · no account needed
Share 𝕏 Facebook Reddit LinkedIn Threads WhatsApp Bluesky Mastodon Email

Discussion

0 comments

More from The Hindu — Top